Enbridge Pipelines (NW) Inc. - MV2017L1-0002
Line 21 pipeline replacement (Norman Wells to Zama) near kilometre post (KP) 529 (the project). The project is located near the Mackenzie River, approximately 9 kilometres east of the village of Fort Simpson, in the Dehcho Region of the Northwest Territories.
Note that the pipeline crossing is a segment replacement project for an existing pipeline that is regulated by the National Energy Board (NEB). The replacement segment to be constructed will cross underneath the Mackenzie River at an anticipated depth of 90-110 metres below the river bed. The construction work sites on either side of the river crossing will be above the oridinary high water mark. An application for the project was filed with the NEB on March 10, 2017 and is accessible on the NEBs Public Registry at https://apps.neb-one.gc.ca/REGDOCS/Home/Index.
Associated Land Use Permit: MV2017P0013- All Issuances (2)
- Annual Reports (9)
- Application and Related Docs (23)
- Consultations - Reviews - Work Plans (37)
- Engagement Plan (3)
- Further Study Requested Sec. 22.2.b (1)
- GIS Data (1)
- Interim Closure and Reclamation Plan (4)
- Operations and Notifications (1)
- Preliminary Screening (5)
- Public Hearing (76)
- Security and Water Use Fees (3)
- Sediment and Erosion Control (4)
- Shapefiles (1)
- SNP Program (1)
- Spill - Contingency - Emergency Response (4)
- Technical Session (1)
- Waste Management Plan (6)
- Water Management (7)
Documents
Document | Received/Sent | Uploaded |
---|---|---|
MV2017L1-0002 - Enbridge Pipelines - Minister Approval and WL Issuance Letter - Mar12-18.pdf (256.97 KB) | March 12, 2018 | March 16, 2018 |
MV2017L1-0002 - Enbridge Pipelines NW - Issuance Letter with Licence-Conditions and RFD - Mar9-18.pdf (1.48 MB) | March 9, 2018 | March 13, 2018 |
Document | Received/Sent | Uploaded |
---|---|---|
MV2017P0013 MV2017L1-0002 - Enbridge Pipelines NW Inc. Line 21 Replacement - Work Plan updated - Dec12-17.pdf (57.5 KB) | December 12, 2017 | December 12, 2017 |
Document | Received/Sent | Uploaded |
---|---|---|
MV2017L1-0002 - Enbridge Pipelines - Receipt for Water Use Fee - A744185 - Jun19-18.pdf (185.49 KB) | June 19, 2018 | June 20, 2018 |
MV2017L1-0002 - Enbridge Pipelines - Receipt for water use fees - A744183 - Apr16-18.pdf (142.11 KB) | April 16, 2018 | April 17, 2018 |
MV2017L1-0002 - Enbridge Pipelines - Acceptance of Security Deposit - GNWT-ENR - Apr12-18.pdf (111.17 KB) | April 12, 2018 | April 12, 2018 |
Document | Received/Sent | Uploaded |
---|---|---|
MV2017L1-0002 - Enbridge Pipelines - Request for comments on Request for SNP Revisions from ENR - Mar15-18.pdf (406.66 KB) | March 15, 2018 | March 20, 2018 |
Document | Received/Sent | Uploaded |
---|---|---|
MV2017P0013 Linked with MV2017L1-0002 - Enbridge - Staff Report for Section 22-2-b - May25-17.pdf (139.55 KB) | May 25, 2017 | July 5, 2017 |
Document | Received/Sent | Uploaded |
---|---|---|
MV2017P0013 MV2017L1-0002 - Enbridge - Norman Wells Pipeline - 1981 Report of EA Panel.pdf (4.54 MB) | September 8, 2017 | September 14, 2017 |
MV2017P0013 MV2017L-0002 - Enbridge Pipelines Inc. - s.157.1 Determination - Staff Report and Comments - Aug3-17.pdf (1.77 MB) | August 3, 2017 | August 21, 2017 |
MV2017P0013 MV2017L1-0002 - Enbridge - 157.1 Reasons for Decision - Aug 10_17.pdf (375.2 KB) | August 10, 2017 | August 11, 2017 |
MV2017P0013 MV2017L1-0002 - Enbridge - Review Comment Table with Attached Comments - Aug 3_17.pdf (2.43 MB) | August 3, 2017 | August 8, 2017 |
MV2017P0013 MV2017L-0002 - Enbridge Pipelines (NW) Inc. - s.157.1 Determination.pdf (284.33 KB) | August 4, 2017 | August 4, 2017 |