Suncor Energy Inc. - S22A-001
The purpose of this Project is to conduct abandonment and reclamation activities at Suncor's Tweed Lake M-47, Tweed Lake A-67, and Bele O-35 wellsites southwest and south of Colville Lake, Sahtu Region, Northwest Territories. The program area consists of three leases, access road, and a laydown area. Winter-only construction will be required for an 85 km access road linking the three well sites to Colville Lake. The project will include the following land-use operations:
· Field scouting using helicopter for water sources and other environmental data
· Surface casing vent flow, gas migration, and production casing pressure testing
· Construction of winter access road
· Transport of equipment to sites
· Remediation of impacts identified, as necessary
· Conducting downhole abandonment and cutting and capping of wellheads
· Water diversion and erosion control features, as required
· Selective seeding and/or tree planting of disturbed areas as required and/or approved
· Demobilization of equipment
Document | Received/Sent | Uploaded |
---|---|---|
S22A-001 - Engagement Plan version 2.0 and Reporting - May 23_22.pdf (457.9 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
S22A-001 - Project Spill and Emergency Response Plan version 1.0 - May 23_22.pdf (1.34 MB) | ||
S22A-001 - Suncor Corporate Emergency Response Plan and Spill Contingency Plan for the NWT - May 23_22.pdf (5.81 MB) |
Document | Received/Sent | Uploaded |
---|---|---|
S22A-001 - Waste Management Plan version 1.0 - May 23_22.pdf (8.54 MB) |