GNWT-INF - MV2023X0029
Status:
Issued
Authorization:
Land Use Permit
Activity:
Miscellaneous
Start:
December 15, 2023
Expiry:
December 14, 2028
Staff:
Tyree Mullaney
For the construction of a transmission line to connect Dory Point and the communities of Fort Providence and Kakisa to the Taltso Hydroelectric system at an interconnnection point near Hay River.
Documents
Displaying 1 - 20 of 20
1. Permit - Licence - Other Issuances
Document | Received/Sent | Uploaded |
---|---|---|
GNWT – INF – Transmission List - Issuance - Type A Land Use Permit - Dec 15_23.pdf (954.04 KB) |
2. Initial/Renewal Application
Document | Received/Sent | Uploaded |
---|---|---|
GNWT – INF – Transmission Line - New Type A Land Use Permit - Review Comments and Responses - Dec 1_23.pdf (308.99 KB) | ||
GNWT- INF - Transmission Line - Deadline Extension Request - Responses - Nov1_23.pdf (197.99 KB) | ||
GNWT - INF - Transmissino Line - Request for Extension to Comments - Oct27_23.pdf (185.67 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
GNWT - INF – Transmission Line - Notice of Timeline Pause - Nov 24_23.pdf (196.01 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
GNWT–INF – Transmission Line - Notification - Preliminary Screening Determination - Dec 1_23.pdf (461.59 KB) |
6. Management Plans
Document | Received/Sent | Uploaded |
---|---|---|
GNWT - INF - Transmission Line - Spill Contingency Plan V1.1 - Board Staff Conformity - Dec20_23.pdf (149.18 KB) | ||
GNWT - INF - Transmission Line - Spill Contingency Plan V1.1 - Dec19_23.pdf (2.77 MB) |