For the construction of a transmission line to connect Dory Point and the communities of Fort Providence and Kakisa to the Taltso Hydroelectric system at an interconnnection point near Hay River.
Documents
Displaying 1 - 17 of 17
2. Initial/Renewal Application
Document | Received/Sent | Uploaded |
---|---|---|
GNWT – INF – Transmission Line - New Type A Land Use Permit - Review Comments and Responses - Dec 1_23.pdf (308.99 KB) | December 1, 2023 | December 1, 2023 |
GNWT- INF - Transmission Line - Deadline Extension Request - Responses - Nov1_23.pdf (197.99 KB) | November 1, 2023 | November 1, 2023 |
GNWT - INF - Transmissino Line - Request for Extension to Comments - Oct27_23.pdf (185.67 KB) | October 27, 2023 | November 1, 2023 |
Document | Received/Sent | Uploaded |
---|---|---|
GNWT - INF – Transmission Line - Notice of Timeline Pause - Nov 24_23.pdf (196.01 KB) | November 24, 2023 | November 24, 2023 |
Document | Received/Sent | Uploaded |
---|---|---|
GNWT–INF – Transmission Line - Notification - Preliminary Screening Determination - Dec 1_23.pdf (461.59 KB) | December 1, 2023 | December 1, 2023 |