Northwest Territories Power Corporation - MV2020X0004
Status:
Issued
Authorization:
Land Use Permit
Activity:
Miscellaneous
Start:
July 2, 2020
Expiry:
July 1, 2025
Staff:
Andrew Wheeler
Construction of replacement support facilities and decommissioning of existing facilities as part of theTaltson Hydroelectris Facility overhaul.
Documents
- All Issuances (4)
- Application and Related Docs (29)
- Assorted Management Plans (1)
- Engagement Plan (1)
- External Authorizations (3)
- Inspection Reports (7)
- Modifications (15)
- Operations and Notifications (8)
- Other (3)
- Sediment and Erosion Control (5)
- Spill - Contingency - Emergency Response (2)
- Waste Management Plan (2)
Displaying 1 - 80 of 80
1. Permit - Licence - Other Issuances
Document | Received/Sent | Uploaded |
---|---|---|
Taltson Upgrades - Licence Mod and Permit Project Update Corresponden - May30_22.pdf (2.16 MB) | ||
NTPC - Taltson Upgrades - Notification of Season Start-up - Apr28_21.pdf (100.03 KB) | ||
MV2020X0004 - NTPC - Issuance - Staff Report and Comments - Jul2-20.pdf (2.15 MB) | ||
MV2020X0004 - Northwest Territories Power Corp. - Issuance - Type A Land Use Permit.pdf (786.17 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
NTPC - Taltson - 2022QP0006 - Sand Pit Return - Mar 2_24.pdf (229.86 KB) | ||
NTPC - Taltson - 2022QP0006 - Gravel Pit Return - Mar 2_24.pdf (230.09 KB) | ||
NTPC - Talston - Quarry Permit 2020QP0019 - Verification - Apr11_22.pdf (234.25 KB) |
2. Initial/Renewal Application
3. Amendment Application
5. Reports and Studies
Document | Received/Sent | Uploaded |
---|---|---|
NTPC - Taltson - Inspectorion Report - Sept 9, 2024 - Nov22_24.pdf (10.72 MB) | ||
NTPC - Taltson - Inspection Report - February 20, 2024 - Mar 2_24.pdf (4.99 MB) | ||
NTPC - Taltson - Inspection Report - July 13, 2023 - Aug8_23.pdf (5.97 MB) | ||
NTPC - Taltson - Inspection Report - May 26, 2022 - Jun8_22.pdf (3.98 MB) | ||
NTPC - Taltson - Inspection Report - July 2021 - Aug16_21.pdf (11.62 MB) | ||
NTPC - Taltson Facility Upgrades - Inspection Report - July 2021 - Aug13_21.pdf (11.62 MB) | ||
NTPC - Taltson Upgrades - Notification of Inspection - Email Correspondence - Aug6_21.pdf (160.85 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
NTPC - Taltson - Camp Water Intake - End of Work Notification - Aug2_22.pdf (116.86 KB) | ||
NTPC - Taltson - Turbidity Curtain Installation Complete - Jul25_22.pdf (109.11 KB) | ||
NTPC - Taltson Facility Upgrades - 2022 Start-up Notification - Apr22_22.pdf (383.96 KB) | ||
NTPC - Taltson - Notification - Amendment and modification under WL MV2011L4-0002 - Apr12_22.pdf (359.34 KB) | ||
NTPC - Taltson Upgrades - Notification of Standard Operating Procedure - Aug6_21.pdf (797.69 KB) | ||
NTPC - Taltson Upgrades - Temporary Water Line Correspondence - Mar23-21.pdf (3.85 MB) | ||
NTPC - Taltson Upgrades - Temporary Water Line Figure - Mar23-21.pdf (617.79 KB) | ||
MV2020X0004 - NTPC - Taltson Upgrades - Staging Notification - Feb15-21.pdf (837.79 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
NTPC - Taltson - Type A Permit - SDS Aderex-Dust Control.pdf (8.1 MB) | ||
NTPC - Taltson - Wildlife Survey - Feb4_21.pdf (3.01 MB) | ||
MV2020X0004 - NTPC - Taltson - Wildlife Survey - July2020.pdf (8.86 MB) |
6. Management Plans
Document | Received/Sent | Uploaded |
---|---|---|
NTPC - Taltson Hydro -Secondary Containment Standard Operating Procedure - Aug9_21.pdf (711.75 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
MV2020X0004 - NTPC - Taltson - Engagement Plan - Version 1 - May15-20.pdf (551.88 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
NTPC - Taltson Facility Upgrades - Sediment and Erosion Control Management Plan (V2) - Staff Confirmation - Aug3_21.pdf (155.44 KB) | ||
NTPC - Taltson - Facility Upgrades - Sediment and Erosion Control MP (V1) Resubmission Notification - Jul14_21.pdf (298.37 KB) | ||
NTPC - Resubmission Required - Sediment and Erosion Control Plan V1 - Jun17-21.pdf (146.05 KB) | ||
NTPC - Taltson Facility Upgrades - SECMP - Incomplete - July24_20.pdf (219.97 KB) | ||
NTPC - Taltson - Facility Upgrades - Sediment and Erosion Control Management Plan (V1) - Apr29-21.pdf (15.48 MB) |
Document | Received/Sent | Uploaded |
---|---|---|
NTPC - Taltson Facility Upgrades - Spill Contingency Plan - Staff Confirmation - June3_21.pdf (154.97 KB) | ||
NTPC - Taltson Facility Upgrades- Spill Contingency Plan - May18-21.pdf (4.86 MB) |
Document | Received/Sent | Uploaded |
---|---|---|
NTPC - Taltson Facility Upgrades - Waste Management Plan - May18-21.pdf (8.24 MB) | ||
NTPC - Taltson Facility Upgrades - Waste Management Plan - Staff Confirmation - June3_21.pdf (155.49 KB) |