Government of Yukon - Department of Highways and Public Works - MV2019L8-0013
The Government of the Yukon, Department of Highways and Public Works is proposing the Dempster Fibre Project (DFP), that will see the construction of an approximately 800-km fibre optic line from Dawson City, Yukon, to Inuvik, Northwest Territories. For the purposes of the Land Use Permit and Water Licence application, the project is defined as the section of the DFP located in the Northwest Territories.
The fibre optic cable will enter the Northwest Territories at the Yukon/Northwest Territories border and then travel approximately 271 km north to Inuvik. The project is located entirely within the Gwich'in Settlement Area (GSA), passing through the communities of Fort McPherson and Tsiigehtchic.
Project Components:
- Fibre optic cable and conduit to be installed adjacent to the Dempster Highway along the Right of Way, extending form the Yukon border to Inuvik; and
- Handholes along the route.
The project will connect to an existing terminal facility in Inuvik and to existing buildings in communities along the route to provide service to those communities.
Construction and operation of the project will require the following supporting activities:
- Geotechnical drilling to supplement any potential gaps or unknown conditions that are encountered;
- Use of pre-existing staging areas for equipment and materials (up to five staging areas may be used at one time);
- Construction of temporary camps to accommodate work crews;
- Clearing of vegetation as required in the right of way;
- Installation of conduits and fibre optic cable; and
- Ongoing operations and maintenance.
Documents
- All Issuances (2)
- Annual Reports (4)
- Application and Related Docs (7)
- Assorted Management Plans (12)
- Conceptual Closure and Reclamation Plan (2)
- Consultations - Reviews - Work Plans (5)
- Engagement Plan (3)
- Further Study Requested Sec. 22.2.b (4)
- Interim Closure and Reclamation Plan (1)
- Operations and Notifications (3)
- Preliminary Screening (2)
- Progress Reports (6)
- Security and Water Use Fees (2)
- Sediment and Erosion Control (3)
- Spill - Contingency - Emergency Response (5)
- Waste Management Plan (2)
- WEMP - Wildlife Effects Monitoring Program (4)
Document | Received/Sent | Uploaded |
---|---|---|
MV2019X0027 MV2019L8-0013 - Government of Yukon - Issuance - Staff Report and Comments - Aug20-20.pdf (8.45 MB) | ||
MV2019L8-0013 - Government of Yukon - Issuance - Type B Water Licence.pdf (1.18 MB) |
Document | Received/Sent | Uploaded |
---|---|---|
Gov. of Yukon - Water Use Fees - Receipt No. 283076 - Aug10_22.pdf (53.53 KB) | ||
MV2019L8-0013 - Government of Yukon - Security Letter from GNWT - Dec7_20.pdf (251.66 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
MV2019X0027 MV2019L8-0013 - Yukon Government - Comment Summary Table - Aug20_20.pdf (295.87 KB) | ||
MV2019L8-0013 MV2019X0027 - Government of the Yukon - News North - Oct28_19.pdf (775.61 KB) | ||
MV2019X0027 MV2019L8-0013 - Government of the Yukon - Highways and Public Works - Notice of Application - Oct23_19.pdf (957.21 KB) | ||
MV2019X0027 MV2019L8-0013 - Government of the Yukon - Highways and Public Works - GRRB request review extension - Oct23_19.pdf (99.22 KB) | ||
MV2019L8-0013 - Government of Yukon - Department of Highways and Public - DRAFT Water Licence - Oct16_19.docx (66.17 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
MV2019L8-0013 MV2019X0027 - Yukon Government Response to Information Request - Mar17_20.pdf (1.81 MB) | ||
MV20190027 MV2019L8-0013 - Government of Yukon - Shapefiles - Dec23_19.zip (9.25 MB) | ||
MV2019L8-0013 MV2019X0027 - Government of Yukon - Information Request - Dec 03_19.pdf (204.98 KB) | ||
MV2019L8-0013 MV2019X0027 - Government of Yukon - Transboundary Determination and Request for Further Study - Staff Report.pdf (251.03 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
MV2019X0027 MV2019L8-0013 - Government of Yukon - Notification - Preliminary Screening Determination - Aug20_20.pdf (207.71 KB) | ||
MV2019X0027 MV2019L8-0013 - Government of Yukon - Preliminary Screening Report - Aug20_20.pdf (379.04 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
Gov. of Yukon -Dempster Fibre - 2023 Annual Report - May06_24.pdf (304.31 KB) | ||
Gov. of Yukon - 2022 Annual Report - Mar30_23.pdf (942.2 KB) | ||
Government of Yukon - Annual Report - Mar30_22.pdf (462.78 KB) | ||
Government of Yukon - 2019 and 2020 Annual Report - Jul19_21.pdf (252.16 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
Gov. of Yukon - Water Withdrawal Summary Report 2023 - Oct26_23.pdf (347.21 KB) | ||
Gov. of Yukon - Notice of Work in 2023 - Mar26_23.pdf (172.97 KB) | ||
Gov. of Yukon - Weekly Water Withdrawal Summary Report - Aug3_22.pdf (407.35 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
Gov. of Yukon - Water Withdrawal Summary for DFP for September 10-16 - Sep20_22.pdf (409.14 KB) | ||
Gov. of Yukon - Water Withdrawal Summary for DFP August 27 to September 2 - Sep6_22.pdf (410.63 KB) | ||
Gov. of Yukon - Water Withdrawal Summary for DFP August 20-26 - Aug20_22.pdf (97.51 KB) | ||
Gov. of Yukon - Water Withdrawl Summar for DFP August 13-19 - Aug23_22.pdf (410.78 KB) | ||
Gov. of Yukon - Water Withdrawal Summary for DFP July 30 to Aug 05_22.pdf (404.48 KB) | ||
Gov. of Yukon - Water Withdrawal Summary for DFP July 22 to 29 - Aug01_22.pdf (407.35 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
MV2019X0027 MV2019L8-0013 - Yukon Government - Engagement Plan - Dec18_20.pdf (7.17 MB) | ||
MV2019X0027 MV2019L8-0013 - Government of the Yukon - Engagement Plan V1.1 - Dec8_20.pdf (220.4 KB) | ||
MV2019L8-0013 MV2019X0027 - Government of Yukon - Highways and Public Works - Engagement Plan and Record V1 - Oct3_19.pdf (5.45 MB) |
Document | Received/Sent | Uploaded |
---|---|---|
Gov. of Yukon - Sediment and Erosion Control Plan v2 - Staff Report and Comments - Jul25_22.pdf (667.57 KB) | ||
Gov. of Yukon - Erosion and Sediment Control Plan V2 - Jun9_22.pdf (21.37 MB) | ||
Gov. of Yukon - Sediment and Erosion Control Plan - Apr19_22.pdf (11.26 MB) |
Document | Received/Sent | Uploaded |
---|---|---|
Gov. of Yukon – Emergency Frac-Out Response Plan v1 - Staff Report and Comments - Jul25_22.pdf (614.29 KB) | ||
Gov. of Yukon - Emergency Frac-Out Plan - Apr19_22.pdf (338.72 KB) | ||
MV2019X0027 MV2019L8-0013 - Government of the Yukon - Various Management Plans - Staff Report and Comments.pdf (747.32 KB) | ||
MV2019X0027 MV2019L8-0013 - Government of the Yukon - Spill Contingecy Plan V1.1 - Dec8_20.pdf (1.22 MB) | ||
MV2019L8-0013 MV2019X0027 - Government of Yukon - Highways and Public Works - Spill Contingency Plan V1 - Oct3_19.pdf (458.53 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
MV2019X0027 MV2019L8-0013 - Government of the Yukon - Waste Management Plan V1.1 - Dec8_20.pdf (324.22 KB) | ||
MV2019L8-0013 MV2019X0027 - Government of Yukon - Highways and Public Works - Waste Management Plan V1 - Oct3_19.pdf (383.81 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
Gov of Yukon – Wildlife Management Plan v4 - Staff Report and Comments - Jul25_22.pdf (811.6 KB) | ||
Gov. of Yukon - Wildlife Management and Monitoring Plan V4 - Part 1 - Jun9_22.pdf (9.84 MB) | ||
Gov. of Yukon - Wildlife Management and Monitoring Plan V4 - Part 2 - Jun9_22.pdf (17.13 MB) | ||
Gov. of Yukon - Wildlife Management and Monitoring Plan - Apr20_22.pdf (25.89 MB) |
Document | Received/Sent | Uploaded |
---|---|---|
Gov. of Yukon - Closure and Reclamation Plan v2 - Staff Report and Commnets - Jul25_22.pdf (632.01 KB) | ||
Gov. of Yukon - Closure and Reclamation Plan V2 - Jun9_22.pdf (306.34 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
Gov. of Yukon - Closure and Reclamation Plan - Apr19_22.pdf (300.78 KB) |