Enbridge Pipelines (NW) Inc. - MV2013P0011
Status:
Closed
Authorization:
Land Use Permit
Activity:
Pipeline
Start:
July 18, 2013
Expiry:
July 17, 2020
Staff:
Angela Love
Off right-of-way activities to operate and maintain the Norman Wells (Line 21) pipeline from Norman Wells, NT to the Alberta/Northwest Territories border. Permitted activities include use and maintenance of cleared fireguard areas, seasonal trails and shoo flies, all-weather roads, campsites, workspaces, borrow sites, an airstrip, and application of herbicides.
Previously permitted under MV2006P0018.
Transboundary with Dehcho Region and the Sahtu and Metis Settlement Area.
Displaying 1 - 6 of 6
1. Permit - Licence - Other Issuances
Document | Received/Sent | Uploaded |
---|---|---|
Enbridge - Final Plan and Clearance - Staff Report - Jul25_22.pdf (221.7 KB) | ||
Enbridge - Approval - Final Plan and Clearance - Jul11_22.pdf (190.21 KB) | ||
MV2013P0011 - Enbridge - Inspector Recommendation - Sahtu - July 22_21.pdf (120.35 KB) | ||
MV2013P0011 - Enbridge - Inspector Recommendation - Dehcho - July 22_21.pdf (122.32 KB) | ||
MV2013P0011 - Enbridge - Final Plan Updated - July 9_21.pdf (1.03 MB) | ||
MV2013P0011 - Enbridge - Final Plan - Oct 16_20.pdf (22.82 KB) |