Sambaa Ke Development Corporation Ltd. - MV2012Q0026
Status:
Closed
Authorization:
Land Use Permit
Activity:
Quarrying
Start:
January 23, 2013
Expiry:
January 22, 2018
Staff:
Tyree Mullaney
The project consists of building a 9.85 kilometre ice bridge for the Community of Trout Lake, south easterly and with a 5.5 kilometre winter road along a previous route used in 1991 and again in 2006. The site/source was ground-truthed under two previous LUP Permits, N1990X0443 and MV2007Q0047.
In February and March of 2013 it is planned to execute the work by excavating, load and haul the required 20,000 M3 would be crushed to Airport specifications, 16 mm class and the remaining 5,000 M3 would be left in stockpile.
Displaying 1 - 12 of 12
1. Permit - Licence - Other Issuances
Document | Received/Sent | Uploaded |
---|---|---|
MV2012Q0026 - Sambaa Ke Development Corp - Issuance Letter with conditions - Jan24-13.pdf (1.37 MB) |
Document | Received/Sent | Uploaded |
---|---|---|
MV2012Q0026 - Sambaa Ke Development corp - 2013QP0006 - QP Closure Verification - May3-13.pdf (58.79 KB) | ||
MV2012Q0026 - Sambaa Ke Dev Corp -AANDC Clarification on issuance of QP 2013QP0006 - Jan17-13pdf.pdf (31.65 KB) | ||
MV2012Q0026 - SKDC - AANDC Issued QP 2013QP0006 - Jan16-13.pdf (259 KB) |