DIAND-GIANT - MV2012L8-0010
Status:
Expired
Authorization:
Licence
Activity:
Miscellaneous
Start:
March 28, 2013
Expiry:
November 28, 2020
Staff:
Shannon Allerston
The proposed undertaking includes 2 primary activities (1) deconstruction of the roaster complex and (2) stabilization of underground elements, including arsenic trioxide and non-arsenic trioxide dust filled chambers and stopes, and bulkheads.
Displaying 1 - 5 of 5
6. Management Plans
Document | Received/Sent | Uploaded |
---|---|---|
MV2012L8-0010 MV2016S0016 - DIAND - GIANT - Emergency Management and Response Plan - June10_20.pdf (2.83 MB) | ||
MV2012L8-0010 - AANDC - CARD - Staff Report for Roaster Complex Deconstruction SCP - Jun6-13.pdf (217.17 KB) | ||
MV2012L8-0010 - AANDC - CARD - Roaster Complex Deconstruction SCP Approval - Jun6-13.pdf (397.51 KB) | ||
MV2012L8-0010 - AANDC - CARD - Request for comments on Revised Spill Contingency Plan - May2-13.pdf (228.24 KB) | ||
MV2012L8-0010 - AANDC-CARD - Updated Spill Contigency Plan for Roaster Complex Deconstruction - May1-13.pdf (6.42 MB) |