Construct and operate the portion of the Tibbitt to Contwoyto Winter Road (TCWR) route from the Ekati Mine turnoff on Lac de Gras in the Northwest Territories (NT; Lac de Gras) to the Lupin Mine in Nunavut (NU; Lupin) to mobilize and demobilize equipment and supplies that may be used for ongoing reclamation of Lupin in the Kitikmeot Region of Nunavut (the Program) [traversing 95 km in NT and 118 km in NU (213 km in total)].  

As the route crosses the NT/NU border, this is a transboundary project. 

Documents

Displaying 1 - 31 of 31
E.g., 09/29/2020
E.g., 09/29/2020

1. Permit - Licence - Other Issuances

All Issuances
Document Received/Sent Uploaded
MV2018F0024 - Nahanni Construction Ltd - Issuance with Permit-Conditions and RFD - Type A LUP - Feb28-19.pdf (510.64 KB) February 28, 2019 March 1, 2019
Final Plan and Clearance
Document Received/Sent Uploaded
MV2018F0024 - Nahanni Construction - Approval of Discontinuance - Nov19-19.pdf (214.73 KB) November 19, 2019 November 20, 2019
MV2018F0024 - Nahanni Construction - Final Clearance - Nov19-19.pdf (137.05 KB) November 19, 2019 November 20, 2019
MV2018F0024 - Nahanni Construction - Staff Report - Discontinuance and Final Plan - Nov7-19.pdf (141.29 KB) November 7, 2019 November 15, 2019
Security and Water Use Fees
Document Received/Sent Uploaded
MV2018F0024 - Nahanni Construction Ltd - Security Deposit Acknowledgement Letter - GNWT Lands - Mar4-19.pdf (96.26 KB) March 4, 2019 March 5, 2019
MV2018F0024 - Nahanni Construction - Receipt for New LUP Application Fee - C153080 - Dec18-18.pdf (129.01 KB) December 18, 2018 January 7, 2019

2. Initial/Renewal Application

Application and Related Docs
Document Received/Sent Uploaded
MV2018F0024 - Nahanni Construction Ltd. - Issuance - Staff Report and Comments - Feb28-19.pdf (978.08 KB) February 28, 2019 March 1, 2019
MV2018F0024 - Nahanni Construction Ltd - Confirmation of Contract Awarded to Nahanni - Dec21-18.pdf (69.97 KB) December 21, 2018 February 20, 2019
MV2018F0024 - Nahanni Consturction - Updated Engagment Plan_v3 - Jan17_19.pdf (257.2 KB) January 17, 2019 January 17, 2019
MV2018F0024 - Nahanni Construction - Permission to use Solid Waste Facilities - Jan17_19.pdf (87.24 KB) January 17, 2019 January 17, 2019
MV2018F0024 - Nahanni Construction - Updated Security Estimate_v2 - Jan17_19.pdf (62.85 KB) January 17, 2019 January 17, 2019
MV2018F0024 - Nahanni Construction - Waste Management Plan - Jan17_19.pdf (631.42 KB) January 17, 2019 January 17, 2019
MV2018F0024 - Nahanni Construction - Updated Land Use Permit Application - Jan17_19.pdf (715.69 KB) January 17, 2019 January 17, 2019
MV2018F0024 - Nahanni COnstruction - Updated EngagementSummary - Jan17_19.pdf (212.45 KB) January 17, 2019 January 17, 2019
MV2018F0024 - Nahanni Construction Ltd - Incomplete Application Letter - Dec27-18.pdf (572 KB) December 27, 2018 December 27, 2018
MV2018F0024 - Nahanni Construction Ltd - Confirmation of Eligibility - Information request to GNWT Lands - Dec19-18.pdf (110.57 KB) December 19, 2018 December 20, 2018
MV2018F0024 - Nahanni Construction - New LUP Application - Dec17-18.pdf (5 MB) December 17, 2018 December 18, 2018
Consultations - Reviews - Work Plans
Document Received/Sent Uploaded
MV2018F0024 - Nahanni Construction Ltd. - Draft Land Use Permit Conditions.docx (159.27 KB) January 25, 2019 January 25, 2019
Preliminary Screening
Document Received/Sent Uploaded
MV2018F0024 - Nahanni Construction Ltd - Issuance - Preliminary Screening - Feb28-19.pdf (249.64 KB) February 28, 2019 March 1, 2019

3. Amendment Application

Application and Related Docs
Document Received/Sent Uploaded
MV2018F0024 - Nahanni Construction Ltd - Notice of Discontinuance - Oct4_19.pdf (183.17 KB) October 7, 2019 October 7, 2019
Consultations - Reviews - Work Plans
Document Received/Sent Uploaded
MV2018F0024 - Nahanni Construction Ltd. - Inspector Recommendations for Discontinuance and Final Clearance - Oct7_19.pdf (152.57 KB) October 7, 2019 October 7, 2019

5. Reports and Studies

Operations and Notifications
Document Received/Sent Uploaded
MV2018F0024 - Nahanni Construction Ltd - Discussion on Staging Equipment - Mar7-19.pdf (66.23 KB) March 7, 2019 March 13, 2019

6. Management Plans

Assorted Management Plans
Document Received/Sent Uploaded
MV2018F0024 - Nahanni Construction - New LUP Application - Wildlife Protection Plan - Dec17-18.pdf (562.86 KB) December 17, 2018 December 18, 2018
MV2018F0024 - Nahanni Construction - New LUP Application - Abandonment and Restoration Plan - Dec17-18.pdf (481.18 KB) December 17, 2018 December 18, 2018
Engagement Plan
Document Received/Sent Uploaded
MV2018F0024 - Nahanni Consturction - Updated Engagment Plan_v3 -- Jan17_19.pdf (257.2 KB) January 17, 2019 January 17, 2019
MV2018F0024 - Nahanni COnstruction - Updated EngagementSummary -- Jan17_19.pdf (212.45 KB) January 17, 2019 January 17, 2019
MV2018F0024 - Nahanni Construction - New LUP Application - Engagement Plan - Dec17-18.pdf (216.67 KB) December 17, 2018 December 18, 2018
Spill - Contingency - Emergency Response
Document Received/Sent Uploaded
MV2018F0024 - Nahanni Construction - New LUP Application -Spill Continency Plan - Dec17-18.pdf (581.01 KB) December 17, 2018 December 18, 2018
Waste Management Plan
Document Received/Sent Uploaded
MV2018F0024 - Nahanni Construction - Waste Management Plan -- Jan17_19.pdf (631.42 KB) January 17, 2019 January 17, 2019
MV2018F0024 - Nahanni Construction - Permission to use Solid Waste Facilities -- Jan17_19.pdf (87.24 KB) January 17, 2019 January 17, 2019

9. GIS Data

GIS Data
Document Received/Sent Uploaded
MV2018F0024_Route_Layers_20181228.zip (34.96 KB) January 17, 2019 January 17, 2019