​The proposed project is a repair of the existing UBC Bri dge. The bridge will be repaired by replacing thesubstructure of the bridge with piles and caps designed to withstand identified lateral earth pressure being placed on the bridge from the movement of fill materials surrounding the abutments.

The bridge deck and steel girders of the current bridge structure will be re-used. No in-stream work is required to complete the bridge repair. The contractor will mobilize the equipment to site. 

The contractor may set-up a temporary office structure near the UBC Bridge location to support repair operations; this will be removed once repairs are complete .

Documents

Displaying 1 - 19 of 19
E.g., 09/18/2019
E.g., 09/18/2019

1. Permit - Licence - Other Issuances

All Issuances
Document Received/Sent Uploaded
MV2017X0030 - INAC - CARD - Giant - New LUP Application - Issuance Letter with Permit-Conditions and RFD - Sept28-17.pdf (1.25 MB) September 28, 2017 October 3, 2017

2. Initial/Renewal Application

5. Reports and Studies

Annual Reports
Document Received/Sent Uploaded
MV2017X0030 MV2017L8-0006 - DIAND - GIANT - Annual Water Discharge 43-1 - Inspector Sep10_19.pdf (174.76 KB) September 10, 2019 September 10, 2019
Inspection Reports
Document Received/Sent Uploaded
MV2017X0030 - INAC-CARD GIANT Mine UBC Bridge Project - Inspection Report for April 12 2018 - INAC - apr16-18.pdf (432.68 KB) April 16, 2018 April 17, 2018
MV2017X0030 - INAC CARD - GIANT - Inspection Report for March 12th 2018 - INAC Inspector - Mar16-18.pdf (578.64 KB) March 16, 2018 March 16, 2018

6. Management Plans

Engagement Plan
Document Received/Sent Uploaded
MV2017X0030 - INAC - CARD - Giant - New LUP Application - Engagement Plan - Approval Letter - Sept28-17.pdf (1.25 MB) September 28, 2017 October 3, 2017
MV2017X0030 MV2017L8-0006 - INAC-CARD - Giant Mine - Engagement Plan - Aug14-17-2.pdf (1.37 MB) August 14, 2017 August 14, 2017
Spill - Contingency - Emergency Response
Document Received/Sent Uploaded
MV2017X0030 - INAC - CARD - Giant - New LUP Application - Spill Contingency Plan - Approval Letter - Sept28-17.pdf (1.25 MB) September 28, 2017 October 3, 2017
MV2017X0030 MV2017L8-0006 - INAC-CARD - Giant Mine - Spill Contingency Plan - Aug14-17.pdf (9.39 MB) August 14, 2017 August 14, 2017
Waste Management Plan
Document Received/Sent Uploaded
MV2017X0030 - INAC - CARD - Giant - New LUP Application - Waste Management Plan - Approval Letter - Sept28-17.pdf (1.25 MB) September 28, 2017 October 3, 2017
MV2017X0030 MV2017L8-0006 - INAC-CARD - Giant Mine - Waste Management Plan - Aug14-17.pdf (2.08 MB) August 14, 2017 August 14, 2017