The proposed undertaking includes 2 primary activities (1) deconstruction of the roaster complex and (2) stabilization of underground elements, including arsenic trioxide and non-arsenic trioxide dust filled chambers and stopes, and bulkheads.
Documents
Displaying 1 - 5 of 5
6. Management Plans
Document | Received/Sent | Uploaded |
---|---|---|
MV2012L8-0010 MV2016S0016 - DIAND - GIANT - Emergency Management and Response Plan - June10_20.pdf (2.83 MB) | June 10, 2020 | June 11, 2020 |
MV2012L8-0010 - AANDC - CARD - Staff Report for Roaster Complex Deconstruction SCP - Jun6-13.pdf (217.17 KB) | June 5, 2013 | June 5, 2013 |
MV2012L8-0010 - AANDC - CARD - Roaster Complex Deconstruction SCP Approval - Jun6-13.pdf (397.51 KB) | June 5, 2013 | June 5, 2013 |
MV2012L8-0010 - AANDC - CARD - Request for comments on Revised Spill Contingency Plan - May2-13.pdf (228.24 KB) | May 1, 2013 | May 1, 2013 |
MV2012L8-0010 - AANDC-CARD - Updated Spill Contigency Plan for Roaster Complex Deconstruction - May1-13.pdf (6.42 MB) | May 1, 2013 | May 1, 2013 |