Taltson Hydroelectric Facility Transmission Line - Brushing and maintenance of the existing right of way for the transmission lines from the Taltson Hydroelectric Facility to Pine Point, Fort Resolution, and Fort Smith. Use of equipment. Drilling to identify the main cause(s) of anchor degradation along the Transmission Line.


Uploaded On or After
Uploaded On or Before
Displaying 1 - 23 of 23
1. Permit - Licence - Other Issuances
All Issuances
Document Received/Sent Uploaded
NTPC - Taltson Powerline - Issuance - Type A Land Use Permit - Nov8_22.pdf (954.93 KB)
2. Initial/Renewal Application
Application and Related Docs
Document Received/Sent Uploaded
NTPC - Taltson - New Type A LUP Application - Sep19_22.pdf (5.86 MB)
NTPC - Taltson - Engagement Plan - Sept19_22.pdf (321.96 KB)
NTPC - Taltson - Engagement Log - Sept19_22.pdf (2.28 MB)
NTPC - Taltson - Spill Contingency Plan V1.1 - Sept19_22.pdf (2.22 MB)
NTPC - Taltson - Waste Management Plan V1.1 - Sept19_22.pdf.pdf (11.16 MB)
NTPC - Taltson - Erosion and Sediment Control Plan - Sept19_22.pdf.pdf (379.98 KB)
NTPC - Taltson - Wildlife Avoidance and Mitigation - Sept19_22.pdf.pdf (576.82 KB)
Draft Conditions.pdf (322.02 KB)
NTPC - New Permit Application - Incomplete - Sept12_22.pdf (191.74 KB)
NTPC - Taltson - New Type A LUP Application - Sep7_22.pdf (1.5 MB)
NTPC - Taltson - Engagement Plan - Sep7_22.pdf (320.31 KB)
NTPC - Taltson - Application - Engagement Log - Sep7_22.pdf (2.1 MB)
NTPC - Taltson - Spill Contingency Plan - V.11 - Sep7_22.pdf (2.39 MB)
NTPC - Taltson - Waste Management Plan V.11 - Sep7_22.pdf (11.01 MB)
NTPC - Taltson - Erosion and Sediment Control Plan - Sep7_22.pdf (372.32 KB)
NTPC - Taltson - Wildlife Avoidance and Mitigation Plan - Sep7_22.pdf (576.82 KB)
NTPC - Taltson - Application - Figures L150 Re-Anchor Study - Sep7_22.pdf (4.06 MB)
Preliminary Screening
Document Received/Sent Uploaded
NTPC – Taltson Powerline - Notification - Preliminary Screening Determination - Oct28_22.pdf (500.95 KB)
5. Reports and Studies
Inspection Reports
Document Received/Sent Uploaded
NTPC - Taltson Powerline - Inspection Report - January 11, 2023 - Jan27_23.pdf (1.58 MB)
Operations and Notifications
Document Received/Sent Uploaded
NTPC - Taltson Powerline - Phase 1 Notification - Anchor Excavation Locations - Jan11_23.pdf (2.51 MB)
NTPC - Taltson Powerline - Phase 2 Notification - Borehole Locations - Jan11_23.pdf (3.25 MB)
NTPC- Taltson Powerline Maintenance - Start Up Notification - Dec9_22.pdf (243.92 KB)