Northwest Territories Power Corporation - MV2020X0004
Status:
Issued
Authorization:
Land Use Permit
Activity:
Miscellaneous
Start:
July 2, 2020
Expiry:
July 1, 2025
Staff:
Shannon Allerston
Construction of replacement support facilities and decommissioning of existing facilities as part of theTaltson Hydroelectris Facility overhaul.
Documents
Displaying 1 - 6 of 6
5. Reports and Studies
Document | Received/Sent | Uploaded |
---|---|---|
NTPC - Taltson Facility Upgrades - 2022 Start-up Notification - Apr22_22.pdf (383.96 KB) | April 22, 2022 | April 22, 2022 |
NTPC - Taltson - Notification - Amendment and modification under WL MV2011L4-0002 - Apr12_22.pdf (359.34 KB) | April 12, 2022 | April 12, 2022 |
NTPC - Taltson Upgrades - Notification of Standard Operating Procedure - Aug6_21.pdf (797.69 KB) | August 6, 2021 | August 9, 2021 |
NTPC - Taltson Upgrades - Temporary Water Line Correspondence - Mar23-21.pdf (3.85 MB) | March 23, 2021 | April 6, 2021 |
NTPC - Taltson Upgrades - Temporary Water Line Figure - Mar23-21.pdf (617.79 KB) | March 23, 2021 | April 6, 2021 |
MV2020X0004 - NTPC - Taltson Upgrades - Staging Notification - Feb15-21.pdf (837.79 KB) | February 15, 2021 | February 16, 2021 |